Locomotive Horn Sounding
• The
compliance date of the time-based locomotive horn sounding requirements has
been extended to December 15, 2006. (Please refer to section 222.21(b) for
more information.)
• The locomotive horn must be sounded in a time-based manner at private and
pedestrian crossings, if State law requires locomotive horn sounding at
these crossings. (Please refer to sections 222.25 and 222.27 for more
information.)
• A “good faith” exception has been added to the 20-second maximum
locomotive horn sounding requirement for locomotive engineers who are unable
to precisely estimate their time of arrival at an upcoming grade crossing.
(Please refer to section 222.21(b) for more information.)
• An exception to the 15-second minimum locomotive horn sounding requirement
has been added to the final rule for trains that resume movement after
having been stopped in close proximity to a public highway-rail grade
crossing. (Please refer to section 222.21(d) for more information.)
Locomotive Audible Warning Devices
• Locomotive audible warning devices (other than the locomotive horn) must
be sounded in a time-based manner at public, private and pedestrian
crossings, if State law requires the sounding of locomotive audible warning
devices at these crossings. (Please refer to sections 222.21(e), 222.25, and
222.27 for more information.)
Quiet Zone Notification Requirements
• The public authority must provide a Notice of Intent before submitting an
application for FRA approval of a quiet zone. (Please refer to section
222.39(b) for more information.)
• Pre-Rule Quiet Zones and Pre-Rule Partial Quiet Zones: The public
authority must submit a Notice of Intent by February 24, 2008 and a detailed
plan for quiet zone improvements by June 24, 2008, in order to prevent the
resumption of locomotive horn sounding on June 24, 2008. (Please refer to
section 222.41(c) for more information.)
Locomotive Horn Sound Level
Requirements
• Locomotives used in rapid transit operations on the
general railroad system are exempt from the locomotive horn sound level and
testing requirements contained in section 229.129. (Please refer to section
229.129(d) for more information.)
• The compliance deadline for sound level testing of new
locomotives has been extended to September 18, 2006. (Please refer to
section 229.129(b) for more information.)
• The test site parameters for locomotive horn sound level
testing have been revised. (Please refer to section 229.129(c)(5) for more
information.)
• The requirement to record air flow measurements taken
during locomotive horn sound level testing has been removed. (Please refer
to section 229.129(c)(10) for more information.)
• The final rule has been revised to address sound level
testing of replacement locomotive horns. (Please refer to section
229.129(b)(4) for more information.)
Disclaimer: This summary of
changes in the amended final rule is for informational purposes only.
Entities subject to the rule should refer to the rule text as published in
the Federal Register on August 17, 2006. Should any portion of this summary
conflict with the rule, the language of the rule shall govern.
http://www.fra.dot.gov/us/content/1318